Started wall 93 and 101, place masonry block. Pointed out type IV wall and that at end of wall, at 2 feet need additional rebar. The access openings are 4 ft instead of 3 so some rebar must be cut. Need to schedule 3 regs str grout pours(20 yd3, from Cemex-Irvine, 10am,mix1520533, Monday,Wednesday and Friday of next week)