Friday, October 7, 2011

Clear cool

Started wall 93 and 101, place masonry block.   Pointed out type IV wall and that at end of wall, at 2 feet need additional rebar. The access openings are 4 ft instead of 3 so some rebar must be cut.  Need to schedule 3 regs str grout pours(20 yd3, from Cemex-Irvine, 10am,mix1520533, Monday,Wednesday and Friday of next week)

RAYCON
Diego Mercado MF F250 8H46907
Hector magdeleno M
Armando magdeleno M
Martin Ramirez M
Andres Flores M
Tomas Molina M
Rigoberto Meza AM
Jeff Salazar LF
Ondrej Zafranek L
Juan Mendoza L
Water truck
Grout mixer
Water pump
2 Forklifts