Monday, October 31, 2011

Friday, October 28, 2011

fix at additional 5ft of rw 485

Front


rw485 punch list

Whip blast, chamfer rough edges on barrier, fix chips and cracks


review of soundwall

Re 485 front


Friday, October 21, 2011

Cool cloudy in am

Continued to place SW 83 masonry block.  Reycon directed by Powell at Caltrans request to limit height of new work in case octa and sc decide to cancel wall.


Thursday, October 20, 2011

cool cloudy

Placed grout and high strength grout for SW 83. Continued placing masonry block, David Nguyen was Caltrans Structures Representative. Pour started at 10am continued through 12:00




Wednesday, October 19, 2011

cool clear

Continued placing RW 83.

Click for Yorba Linda, California Forecast

Tuesday, October 18, 2011

photos cool cloudy

Finished sw 93 and 101, 30% done with 83


Wednesday, October 12, 2011

Tags for masonry

Spoke to Nathan of Mets.  Told him no tags.  Asked paul zolezzi to send letter from Mets saying no testing and wc results to me and Nathan

Photos





Clear cool, continued placing 2nd lift set 93 , 101, and 20 ft of 83

Continued wall 93 and 101, place masonry block.   pour 10am on Wednesday

RAYCON
Diego Mercado MF F250 8H46907
Hector magdeleno M
Armando magdeleno M
Martin Ramirez M
Andres Flores M
Tomas Molina M
Rigoberto Meza AM
Pedro Rodriguez l
Vincent oleo l

Jeff Salazar LF
Ondrej Zafranek L
Juan Mendoza L
Oscar Valenzuela L weds only
Pablo garcia L weds only pumper
Water truck
Grout mixer
Water pump
2 Forklifts


Monday, October 10, 2011

Clear cool

Click for Yorba Linda, California Forecast


Placed grout for first lift of wall 93 and 101.  Pour started at 11:00 ended at 1:20
RAYCON
Diego Mercado MF F250 8H46907
Hector magdeleno M
Armando magdeleno M
Victor Oleo M
Pedro Rodriguez M
Martin Ramirez M
Andres Flores M
Tomas Molina M
Rigoberto Meza AM
Jeff Salazar LF
Ondrej Zafranek L
Juan Mendoza L
Water truck
Grout mixer
Water pump
2 Forklifts

Oscar Valenzuela Pump Operator +concrete pump

Friday, October 7, 2011

Clear cool

Started wall 93 and 101, place masonry block.   Pointed out type IV wall and that at end of wall, at 2 feet need additional rebar. The access openings are 4 ft instead of 3 so some rebar must be cut.  Need to schedule 3 regs str grout pours(20 yd3, from Cemex-Irvine, 10am,mix1520533, Monday,Wednesday and Friday of next week)

RAYCON
Diego Mercado MF F250 8H46907
Hector magdeleno M
Armando magdeleno M
Martin Ramirez M
Andres Flores M
Tomas Molina M
Rigoberto Meza AM
Jeff Salazar LF
Ondrej Zafranek L
Juan Mendoza L
Water truck
Grout mixer
Water pump
2 Forklifts

How to remedy transition

Stopped with Elias.  He will look up patching method.  Btw that and grinding,  we will leave it.  Can't make transition great on back be wise of diff style of walls and location of initial exp joints.


Thursday, October 6, 2011

Work stopped due to rain

Work ended early at 1100am yesterday

Wednesday, October 5, 2011

Staging block and scaffolding

Since last Thursday.  Jeff salazar Lf, Juan Mendoza l, ondrej safranek l, 2 forklifts (kp8n9l and y5) 8 hours.  Will start laying tomorrow. 

Cloudy, may rain soon