Met with Rick Engle (CT) and John Bearer (Brutoco foreman) on site to get scope of assignment. Will cover for Rick for Thursday, Friday and Monday. John asked that I be there at 7:00am to get permission to start reinstalling backfill. Thursday testing scheduled for 9:00am with 2:00pm also scheduled in case of problems with the morning test. I will continue with this schedule. Rick asked John where removed mat'l was going to be placed. Warned him that it could not be within 1 foot of the wall because it did not meet Struct Backfill specs.
sunny, clear 65 d F
Rejected material excavated, new material placed up to 4 feet, Will be tested at 9:00am 2/4.
Foreman John Bearer
2 Dump trucks/Owner-Operators
Savala 330C Excavator/Operator
HAMM 3307 Sheepsfoot Roller/Operator
CAT 450G Scraper/Operator
Operators
-B Podanski
-G Jones
-?
4 Laborers
-M Laurer
-L Sanabia
-D Faulkner
-K Gilliam
Shift from 7:00am to 5:30pm