Tuesday, February 9, 2010

4300

zone  2 nail 1


 

Monday, February 8, 2010

6805

Called vaskin and john at brutoco to tell them about tests.  John will tell tim.

6805

Calvin called from the lab.  Fridays compaction passed 96% , thursday 's se failed at 15%

4300 soil nail verification

Starting in zone 3, sta 5315 nail started to pull out went to next one

Friday, February 5, 2010

WPrado Falsework

Discussed FW with Craig Maxwell and Vaskin Kuyumjian. Most issues are ironed out. Will check his modifications on monday. Still questions about bearing of stringers on bent caps.

6805

No new matl added. The material on the top of the stockpile was clayey and full of rocks per John Bearer, BRUTOCO. Tested for se and compaction at 900.  1st lift (2 ft) 1st 2/3ds of wall.  Housekeeping, fill snap tie holes, replace mesh. Protect w gravel bags while discussing bf detail w vaskin.  Select Electric fixed pipe yesterday.  Canceled testing at 2:00pm today and 9:00 am monday because they are not adding new material today.

3215

Drill and grout nails 3 and 4 on top lift.  Tie mesh 3460 to eow first lift.  55f cool cloudy. See Hamid Biglaris diary for afternoon work.

Thursday, February 4, 2010

6805

Rjected matl removed sta 7450 to di @ 7220 weds.  Approved to reinstall bf.  Start placing this section at 7:30am continue removing remaining rejected material, expect finish remval today.  Worked 7 to 430 savala excav 9 to 430 yesterday.  Working to 430 today.

Wednesday, February 3, 2010

Click for Yorba Linda, California Forecast
test

6805

Met with Rick Engle (CT) and John Bearer (Brutoco foreman) on site to get scope of assignment. Will cover for Rick for Thursday, Friday and Monday. John asked that I be there at 7:00am to get permission to start reinstalling backfill. Thursday testing scheduled for 9:00am with 2:00pm also scheduled in case of problems with the morning test. I will continue with this schedule. Rick asked John where removed mat'l was going to be placed. Warned him that it could not be within 1 foot of the wall because it did not meet Struct Backfill specs.

sunny, clear 65 d F

Rejected material excavated, new material placed up to 4 feet, Will be tested at 9:00am 2/4.

Foreman John Bearer
2 Dump trucks/Owner-Operators
Savala 330C Excavator/Operator
HAMM 3307 Sheepsfoot Roller/Operator
CAT 450G Scraper/Operator
Operators
-B Podanski
-G Jones
-?

4 Laborers
-M Laurer
-L Sanabia
-D Faulkner
-K Gilliam

Shift from 7:00am to 5:30pm