Tuesday, February 9, 2010
Monday, February 8, 2010
Friday, February 5, 2010
WPrado Falsework
6805
No new matl added. The material on the top of the stockpile was clayey and full of rocks per John Bearer, BRUTOCO. Tested for se and compaction at 900. 1st lift (2 ft) 1st 2/3ds of wall. Housekeeping, fill snap tie holes, replace mesh. Protect w gravel bags while discussing bf detail w vaskin. Select Electric fixed pipe yesterday. Canceled testing at 2:00pm today and 9:00 am monday because they are not adding new material today.
3215
Drill and grout nails 3 and 4 on top lift. Tie mesh 3460 to eow first lift. 55f cool cloudy. See Hamid Biglaris diary for afternoon work.
Thursday, February 4, 2010
6805
Rjected matl removed sta 7450 to di @ 7220 weds. Approved to reinstall bf. Start placing this section at 7:30am continue removing remaining rejected material, expect finish remval today. Worked 7 to 430 savala excav 9 to 430 yesterday. Working to 430 today.
Wednesday, February 3, 2010
6805
sunny, clear 65 d F
Rejected material excavated, new material placed up to 4 feet, Will be tested at 9:00am 2/4.
Foreman John Bearer
2 Dump trucks/Owner-Operators
Savala 330C Excavator/Operator
HAMM 3307 Sheepsfoot Roller/Operator
CAT 450G Scraper/Operator
Operators
-B Podanski
-G Jones
-?
4 Laborers
-M Laurer
-L Sanabia
-D Faulkner
-K Gilliam
Shift from 7:00am to 5:30pm